Thursday, October 17, 2013

Linkbrige Gates & Lobby Door Update

One of the key security items agreed at the last AGM was the installation of access controlled gates and doors at the Link Bridges and Lobby areas along with CCTV to monitor those entrance/exits

Its frustrating that progress is slow although we are pleased to confirm that work has started.

CCTV & Access Control Works
IMG-20131005-00019_640x480
IMG-20131005-00020_640x480
IMG-20131005-00021_640x480
Since these were taken more work has commenced in other blocks in preparation for the installation of the ironwork/glass doors

Iron Work/Doors
We are in the final stages of the tender process and hope to immanently award the contract. 

The JMC were recently reviewing samples of the proposed ironwork (without the glossed finish)
IMG-20131016-00039_640x480

We aim to try and complete the all blocks in one go however this will depend on the final cost and budget available.

No comments:

Post a Comment