Tuesday, December 10, 2013

Lift Interior Update

We have recently encountered some delays to the lift interior renovation works owing to sub-contractor & materials issues.

The works are due to recommence next week and a revised plan is available to view and the contractor will increase manpower at the site meaning that the latest plan will actually see the project completed early.

In addition to the new interior we are also upgrading the door safety sensors to the full height variant, meaning that an infra-red sensor running along the full height of the doors will prevent them from closing if an obstruction is present.

This will prevent the current situation when the doors can close, giving people or their bags a big whack!